Homeowners · Buyers of new homes

Building defect and dispute reports in Hobart

When new building work cracks, sags, moves or doesn't match the engineer's drawings, an independent structural engineer's report sets out what is wrong, the likely cause and what a proper fix involves. Use it to talk to your builder, or as evidence in a Tasmanian building dispute, mediation or TASCAT.

Fixed quoteper job, agreed before we start
1–2 hrsto a fixed quote
6 yearsto claim after practical completion
Printed defect report with crack photos beside a crack gauge, glasses, a red pen and a laptop showing plans on a timber desk

Independent

We report the facts. We never sell, recommend or carry out the repair.

Fixed quote in 1–2 business hours

Get a fixed quote for a defect report

Tell us what's wrong, when the work was finished and whether a dispute has started.

Fixed quote for your job. No obligation. Or call 03 6146 4747

Photos or plans optional · up to 5 files · Max 50 MB each

Licensed in TasmaniaEngineer – Civil · [licence no.]
Signed by a structural engineer[CPEng / NER]
Fixed quote per jobPrice fixed before we start
IndependentWe never sell or carry out repairs

In short

A building defect report is an independent structural engineer's assessment of building work that may be defective: what the defect is, its likely cause, whether the work matches the drawings and standards, and what a proper fix involves. In Tasmania, residential building contracts of $20,000 or more carry statutory warranties, and claims can be brought within 6 years of practical completion. Priced by fixed quote.

Fee
Fixed quote per job, within 1–2 business hours
You receive
Defect register, likely causes and a rectification scope
Time limit
Claims within 6 years of practical completion

Overview

What is a building defect report?

A building defect report is an independent structural engineer's assessment of building work that may be defective. It records what is wrong, measures it, explains the likely cause, compares the work with the approved drawings and the relevant standards, and sets out what a proper fix involves.

Defect reports are usually about new homes, extensions and renovations: a slab that has cracked and stepped, a floor that bounces, a beam that sags, a deck that moves, or a retaining wall leaning soon after it was built. Some owners use the report to talk to their builder. Others need it for a builder dispute, mediation or the Tasmanian Civil and Administrative Tribunal (TASCAT).

We are independent. We don't build, we don't sell repairs and we don't recommend contractors, so the report is about the work, not a job for us.

Weatherboard cottage with a new timber-framed second storey under construction, scaffolding around it and kunanyi / Mount Wellington behind
Figure 1Structural defects are cheapest to fix before linings go on. A report during construction can stop a problem being built in.

Building defects in Tasmania

What are your rights for defective building work in Tasmania?

Your rights for defective residential building work in Tasmania come mainly from the Residential Building Work Contracts and Dispute Resolution Act 2016, which covers contracts of $20,000 or more.

The Act at a glanceWhat it says
Contracts coveredResidential building work contracts of $20,000 or more (s9)
Statutory warrantiesBuilt into every covered contract (ss23–30)
Later ownersAlso benefit from the warranties (s31)
Time limitClaims within 6 years of practical completion (s32)
Starting a disputeNotice to the Director of Building Control within 6 years (s47)
The Director's decisionAccept or reject the dispute within 10 business days (s48)
Resolving itMediation (s49), then TASCAT (ss58–60)

Not legal advice

We are engineers, not lawyers. This is a general summary of the Act; get legal advice for your situation. CBOS split into Building Standards Tasmania and Consumer Affairs Tasmania on 1 October 2026, so check which agency now handles your dispute.

The usual path of a builder dispute

  1. Is the contract worth $20,000 or more?

    Check the contract price on your signed contract.

    Yes → The Act's warranties and dispute process apply. Go to 2No → Get legal advice on other options
  2. Has the builder fixed the defect after you raised it in writing?

    An engineer's report makes the problem and the fix specific.

    Yes → Ask us to check the repair if you want certaintyNo → Give notice to the Director of Building Control. Go to 3
  3. Did the Director accept the dispute?

    The decision comes within 10 business days.

    Yes → Mediation. Go to 4No → Get legal advice on other options
  4. Did mediation resolve it?

    The defect report gives both sides the same facts to work from.

    Yes → The agreed fix goes aheadNo → The dispute can go to TASCAT

What we assess

Which building defects can a structural engineer assess?

A structural engineer assesses defects in the parts of a building that carry load or hold back ground. These are the structural defects we report on most.

Slabs and footings

Cracked or stepped slabs, settlement on poorly compacted fill, footings shallower or smaller than drawn.

Cracking in new homes

Wall and ceiling cracks rated against the AS 2870 damage categories, with the likely cause.

Framing

Sagging beams, bouncy floors, notched members, missing bracing or tie-downs.

Retaining walls

Walls leaning, cracking or built without the drainage or footing on the design.

Decks and balconies

Movement, bounce, corroded fixings and connections that differ from the details.

Not built to the drawings

Members, spans, footings or connections checked against the approved engineering.

Outside our scope: finishes, waterproofing membranes, roofing, plumbing and electrical defects, except where they are causing structural damage.

Building defect report · Defect register extractExample only · illustrative data, not a real property
Example
PropertyExample new home, Suburb
WorkNew house, recently completed
DocumentsContract, drawings, engineering
AccessInside, outside, subfloor
RefLocationObservationMeasuredLikely causePriority
DF-01Garage slabCrack across slab with a step2 mm wide, 3 mm stepSettlement of fill under the slab edgeRectify
DF-02Living roomCeiling sag below a beam18 mm over 4.2 mBeam smaller than on the drawingsRectify now
DF-03Rear deckLedger fixed with fewer bolts than detailed4 of 9 boltsNot built to the drawingsRectify now
DF-04Bedroom 2Fine crack at window corner<0.1 mmShrinkage of the framingCosmetic

Findings (example)

  • Summary: two items do not match the approved engineering, one is settlement of fill, and one is cosmetic.
  • Rectification scope: what each fix involves, in terms any licensed builder can price, with the items needing an engineer's design or inspection marked.

Illustrative example only, not a real property or result. Every report also lists the documents reviewed, the scope and limits, and is signed by the engineer.

How it works

How does a building defect report work?

A defect report starts with the documents, then the site, then a report that ties the two together.

  1. Step 1

    Send photos and documents

    What's wrong, when the work was finished and whether a dispute has started.

  2. Within 1–2 business hours

    Get a fixed quote

    The scope, the inspection date and the report date, before we start.

  3. On site

    Inspect and measure

    Each defect located, measured and photographed, and checked against the drawings.

  4. On the date in your quote

    Signed report

    Defect register, likely causes, compliance with the drawings and a rectification scope.

What to send us

  • The building contract and any variations
  • Approved drawings and engineering, including any Form 35s
  • Building surveyor documents, such as the Certificate of Likely Compliance
  • The practical completion date, or when you moved in
  • Dated photos of each defect, and when you first noticed it
  • Correspondence with the builder about the defects

Report for TASCAT or mediation?

Say so when you ask for a quote. We set the report out for that use: facts and measurements first, opinions explained, the engineer's qualifications ([CPEng / NER]) and the limits stated.

Choosing a report

Defect report, structural inspection or dilapidation report?

A building defect report is about whether building work was done properly. If your question is different, another report may fit better.

CompareBuilding defect reportStructural inspectionDilapidation report
The questionWas the building work done properly, and what's the fix?What's moving in my house, and does it matter?What condition is the building in before nearby work?
Best forNew homes, extensions, renovations, builder disputesExisting homes with cracks or movementNeighbours of excavation or demolition
OutputDefect register, causes and a rectification scopeLikely cause, severity and recommendationsPhoto log and measured crack register
FromFixed quote$590 + GST$650 + GST

More on structural inspections, dilapidation reports and pre-purchase structural inspections.

Where we inspect

We inspect new and recent building work across Greater Hobart, including growth areas such as Kingston, Bridgewater, Sorell and Howrah. Document reviews from drawings and photos are available Tasmania-wide. See all areas.

Related reading

FAQ

Building defect report FAQs

Still unsure? Call 03 6146 4747 or send photos for a fixed quote.

What is a building defect report?
It is an independent engineer's report on building work that may be defective: what is wrong, the likely cause, whether the work matches the drawings and standards, and what a proper fix involves. Ours focus on the structure.
How long do I have to claim for defective building work in Tasmania?
Under the Residential Building Work Contracts and Dispute Resolution Act 2016, claims under the statutory warranties must be brought within 6 years of practical completion, for contracts of $20,000 or more. Check your dates with a lawyer, because time limits matter.
Can I use your report at TASCAT?
Yes, the report is yours to use. Tell us when you ask for a quote, so it is set out for that purpose, with facts and measurements separate from opinions and the limits stated. We can't predict the outcome of a dispute, and this is not legal advice.
What is the building dispute process in Tasmania?
For contracts covered by the Act, you give notice of the dispute to the Director of Building Control within 6 years, the Director accepts or rejects it within 10 business days, and accepted disputes go to mediation. If mediation doesn't resolve it, the dispute can go to TASCAT.
How much does a building defect report cost?
Defect reports are priced by fixed quote per job, because one cracked slab and a whole house of defects are very different jobs. You get the fixed quote within 1–2 business hours, Monday to Friday.
Do you recommend a builder to fix the defects?
No. We are engineering only: we never sell, recommend or carry out repairs. The report includes a rectification scope that your builder, or another licensed builder, can price and follow.
Do you report on waterproofing, roofing or finishes?
Our reports focus on structural defects. We note non-structural problems where they are causing structural damage, such as a leak softening the ground under a footing, but a building inspector or the relevant trade is better placed to report on finishes.
Can you check the builder's repair afterwards?
Yes. We can re-inspect the rectified work against the scope in our report and confirm what has and hasn't been done. That visit is quoted separately.

Worried about new building work?

Send photos and the contract details. We'll send a fixed price.

Photos or plans are enough to quote. You'll have a fixed quote within 1–2 business hours, with whether the job needs a site visit and when you'll receive it.

Mon–Fri 8:00am–5:00pm · Prices from $350 + GST · Engineering only, independent advice

Call Get a fixed quote