Landslip

Building in a landslip area in Hobart

How to check whether your Hobart block is in a landslip band, what each band changes for approvals, and what a landslip hazard report contains.

Sloping grassy backyard with a curved tension crack in the turf, a leaning power pole and a leaning timber fence, a brick house above and kunanyi / Mount Wellington behind

In short

A Hobart block in a landslip area sits in one of four regulated bands on the state's Landslide Planning Map: low, medium, medium-active or high. Check yours on LISTmap. In any band, low-risk building work becomes notifiable, and Class 1 work in the high band becomes permit work. The higher bands require a geotechnical practitioner's landslip hazard report, prepared to AGS 2007 with an AS 1726-2017 site investigation.

Key takeaways

  • Check LISTmap first. The band on your block, not the suburb, decides which rules apply.
  • In any landslip band, low-risk work becomes notifiable. In the high band, work on a house becomes permit work.
  • A landslip hazard report follows AGS 2007 and rests on an AS 1726-2017 site investigation: boreholes, logs and groundwater.
  • MRT finished an updated map in December 2025, but it had not replaced the statutory overlay when we checked.

Much of Greater Hobart is built on slopes, and some of those slopes have moved before. Tasmania manages the risk with a statewide map and two sets of rules: the Landslip Hazard Code in the planning scheme, and the Director's Determination for building work in landslip hazard areas.

Landslip areas in Hobart: quick facts

Where to check
LISTmap or Risk Ready, landslip hazard layers
Regulated bands
Low, medium, medium-active and high
Approvals
Low-risk work becomes notifiable; high-band house work becomes permit work
Who reports
A geotechnical practitioner, such as a licensed Engineer – Civil
Method
AGS 2007 risk assessment, AS 1726-2017 site investigation
Our fee
Fixed quote per job, within 1–2 business hours

How do you check whether your Hobart block is in a landslip area?

You check the band on the state's landslip mapping, published on LISTmap and the Tasmanian Government's Risk Ready tool. Search the address, turn on the landslip hazard layers and look at the whole lot, not only the house: a block can be partly in a band, and the rules apply to work in that part. Your council's planning scheme overlay shows the same areas, and older declared Landslip A and B areas sit in the high and medium bands.

Under the Building Regulations 2016 (regulation 59), a landslip hazard area is land on the planning scheme's landslip overlay within one of the bands. Outside a band the landslip rules don't apply, although a steep or wet site still needs proper site classification and footing design.

What do the landslip hazard bands mean?

The bands describe how much control the state applies to new building on that land, from no specific controls to strict limits. The Landslide Planning Map sorts all land into five bands. The lowest, Acceptable, carries no landslip controls. The other four form the regulated overlay.

BandWhat it meansWhat changes for building work
AcceptableA landslip is rare here on current understandingNo landslip controls
LowNo mapped landslips, but the land may be susceptibleSpecified and significant work becomes notifiable. Footings engineer-designed unless the AS 2870 report finds the site isn't a problem site for landslip. A landslip report may be asked for
MediumMapped landslip features, a susceptibility zone, or a declared Landslip B areaAs for low, and the AS 2870 site classification must be done by a geotechnical practitioner
Medium-activeKnown recent or active landslipsNotifiable, a landslip hazard report must be prepared, and footings must be designed by an Engineer – Civil licensee
HighA proclaimed Landslip A areaClass 1 work becomes permit work. The permit authority must consider the geotechnical reports, and some work may not be allowed at all

Summarised from the January 2026 landslip fact sheet and the Director's Determination. The medium-active and high bands mark land where a landslip has happened in roughly the last 200 years.

What changes for approvals in a landslip band?

A landslip band lifts work one category: work that would be low risk elsewhere becomes notifiable, so it needs a building surveyor and a Certificate of Likely Compliance. Class 1 work in the high band becomes permit work. Our building approvals guide explains the four categories.

On the planning side, most building work is handled through the building rules instead of the planning code. The Landslip Hazard Code still applies to subdivision, to critical, hazardous and vulnerable uses, to development in the medium-active and high bands, and to significant works in the low and medium bands.

What counts as significant works

Excavation 1 m or deeper (temporary trenches included), cut or fill over 100 m³, clearing more than 1,000 m² of vegetation, storing more than 45,000 litres of water in a pond, tank or pool, changing surface or groundwater drainage, and discharging stormwater or wastewater on the site.

Retaining walls are a common trap. A wall that would be low risk on flat land isn't low risk in a landslip band, so it needs a designed retaining wall and a building surveyor. Our retaining wall rules guide has the height limits.

What does a landslip hazard report contain?

A landslip hazard report shows that the work won't cause or contribute to a landslip on the site or next door, and that it can reach and keep a tolerable level of risk for its life. It is prepared by a geotechnical practitioner: a licensed Engineer – Civil, a geotechnical engineer or an engineering geologist.

The method is the Australian Geomechanics Society's Landslide Risk Management guidelines (AGS 2007), applied through Mineral Resources Tasmania's 2016 guidance on geotechnical reporting. The ground investigation follows AS 1726-2017, the Australian Standard for geotechnical site investigations. A typical report works through these steps:

  1. Step 1

    Desktop review and site mapping

    The band, MRT's landslide inventory, geology and past reports, then slope angles, cracks, seepage and signs of past movement on site.

  2. Step 2

    Site investigation

    Boreholes or test pits, soil and rock logs and groundwater, to AS 1726-2017. Fieldwork may be done with our geotechnical partner, [geotechnical partner].

  3. Step 3

    Risk assessment

    The likely landslide types, how often they could happen and what they would affect, for property and for life, to AGS 2007.

  4. Step 4

    Recommendations and certificate

    Footing type and depth, limits on cut and fill, retaining, drainage and staging, usually certified on a Form 55.

  5. Step 5

    Design and approval

    Footings and walls designed to the report, with a Form 35, then the building surveyor's Certificate of Likely Compliance.

AGS 2007 sets a tolerable risk to life of about 1 in 100,000 per year (10⁻⁵) for new development, stricter than the 1 in 10,000 (10⁻⁴) for existing development. In practice that means footings into firm material, controlled drainage and limits on how much the slope is cut or loaded.

Where have landslides damaged houses in Greater Hobart?

Rosetta and Taroona are the two documented landslide areas in Greater Hobart. Mineral Resources Tasmania records that the Rosetta landslide in Glenorchy has damaged or led to the demolition of 23 houses since 1992. MRT thinks an older, disguised landslide existed there and was reactivated by subdivision and development. The Taroona landslide in Kingborough affected 10 houses and a high school. Statewide, more than 170 buildings have been damaged or destroyed by landslides since the early 1950s.

Taroona also shows why diagnosis matters. A 1977 Department of Mines study of house damage in Taroona found that expansive clay, moisture change and inadequate footings caused most of it, with landslip a less common cause. Cracks on a sloping block are not always a landslip. Our guide to Hobart's reactive clay soils covers the other common cause. Local detail is on our Taroona and Glenorchy pages.

Hand auger with clay on its flights beside a borehole, with soil sample bags and a notebook on a cleared site
Figure 1Boreholes and soil logs are the evidence a landslip hazard report rests on. AS 1726-2017 sets how they are described.

Is the Tasmanian landslip map changing?

Yes, but the update isn't in force as the statutory overlay yet. Mineral Resources Tasmania reviewed the 2013 Landslide Planning Map between February 2024 and December 2025 and published its final report on 18 December 2025. The update keeps the same five bands (acceptable, low, medium, medium-active and high), uses newer data such as a LiDAR-based 10 m elevation model, and adds a recent or active landslides layer.

Statewide, the regulated area grew by 5.6%, mostly in northern council areas. Hobart and Glenorchy saw a reduction in total hazard area, after refinements to rockfall modelling on the lower slopes of kunanyi / Mount Wellington. When we checked in November 2026, MRT said the new mapping will eventually replace the existing statutory mapping and that it is working with the State Planning Office on the process. We could not confirm that it has been adopted, so check both the current overlay and the 2025 map for your block.

Unmapped landslips still count

A council may apply the Landslip Hazard Code to land where it reasonably believes a landslip has happened, even if it isn't mapped, including landslides in MRT's inventory of active landslides.

Can you still build a pool, retaining wall or extension in a landslip band?

Usually yes in the low and medium bands, if the design follows the site classification and any landslip report. What matters is how much you cut, fill, load and wet the slope:

Bushfire-prone land often overlaps steep, vegetated slopes. We don't prepare bushfire assessments: a bushfire hazard practitioner prepares that.

When should you call a structural engineer about landslip?

  • Your block is in a band and you're planning a house, extension, granny flat, pool or wall
  • Your building surveyor or council has asked for a landslip hazard report or engineer-designed footings
  • You can see ground movement: curved cracks in the lawn, leaning fences or poles, new cracks in walls or paths
  • Water is appearing where it didn't before: seepage, soggy ground or a broken pipe on a slope
  • You're buying on a slope in a mapped band and want to know what you could build

Start with the address and your plans

Our landslip reports are priced by fixed quote. Send the address, the band if you know it and any concept plans, and we'll tell you within 1–2 business hours what the job needs and what it costs. Get a fixed quote.

Sources

  1. Department of Premier and Cabinet and State Planning Office, Fact Sheet: Landslip Hazards in the Tasmanian Planning Scheme and Building Act 2016 (15 January 2026). Hazard bands, building controls by band, significant works, landslip hazard report
  2. Mineral Resources Tasmania, Landslide Planning Map Update. Final report on mapping changes and consultation, 18 December 2025, and the status of the statutory overlay
  3. State Planning Provisions, C15.0 Landslip Hazard Code. Bands, exemptions and the geotechnical practitioner (C15.3.1)
  4. Consumer, Building and Occupational Services (now Building Standards Tasmania), Landslip hazard areas. Director's Determination for building in landslip hazard areas
  5. Building Regulations 2016 (Tas), regulation 59. Meaning of landslip hazard area
  6. Tasmania Department of Mines, Unpublished Report 1977/35: House damage in the Taroona area (C. J. Knights)

FAQ

Landslip in Hobart: FAQs

Still unsure? Call 03 6146 4747 or send photos for a fixed quote.

How do I know if my Hobart property is in a landslip area?
Search the address on LISTmap or the Tasmanian Government's Risk Ready tool and turn on the landslip hazard layers, or check the overlay maps in your council's planning scheme. If any part of the lot sits in the low, medium, medium-active or high band, the landslip rules apply to work in that part.
Can I build in a landslip area in Hobart?
Usually yes in the low and medium bands, with a site classification, engineer-designed footings and, where asked for, a landslip hazard report. The medium-active and high bands are far more restrictive, and Class 1 work in the high band is permit work.
Who can prepare a landslip hazard report in Tasmania?
A geotechnical practitioner: a licensed Engineer – Civil, a geotechnical engineer or an engineering geologist with the expertise the Director of Building Control specifies. The report is usually certified for the building surveyor on a Form 55.
What standard does a landslip hazard report follow?
The Australian Geomechanics Society's Landslide Risk Management guidelines (AGS 2007), applied through Mineral Resources Tasmania's 2016 guidance on geotechnical reporting, with the site investigation carried out to AS 1726-2017.
Does a pool or retaining wall in a landslip band need approval?
Usually yes. Excavation 1 m or deeper and a pool holding more than 45,000 litres both count as significant works, and a landslip band takes a retaining wall out of the low-risk category. See our pool on a sloping block guide.
Is the Tasmanian landslip map changing?
Mineral Resources Tasmania finished an updated Landslide Planning Map in December 2025. When we checked in November 2026, MRT said the new mapping will eventually replace the statutory overlay, so check both the current overlay and the 2025 map for your block.
How much does a landslip report cost in Hobart?
We price landslip reports by fixed quote, because the band, slope, access and amount of fieldwork vary a lot between blocks. Send the address and your plans and you'll have a fixed quote within 1–2 business hours.
Are Rosetta and Taroona landslide areas?
Yes. Mineral Resources Tasmania documents the Rosetta landslide in Glenorchy and the Taroona landslide in Kingborough, both of which have damaged houses. Being in either suburb doesn't by itself put a block in a band: check the map for your lot.

Ready when you are

Send a few photos. We'll send a fixed price.

Photos or plans are enough to quote. You'll have a fixed quote within 1–2 business hours, with whether the job needs a site visit and when you'll receive it.

Mon–Fri 8:00am–5:00pm · Prices from $350 + GST · Engineering only, independent advice

Call Get a fixed quote